A contractor was required to recognize income from contracts for the installation of heating and plumbing systems as the progress payments became receivable.
Topics and taglines
d7 import status
Drupal 7 entity type
Node
Drupal 7 entity ID
339572
Extra import data
{
"field_legacy_header": "<strong><em>MNR v. Colford Contracting Co. Ltd.</em></strong>, 60 DTC 1131, [1960] CTC 178 (Ex Ct), briefly aff'd 62 DTC 1338, [1962] CTC 546,",